Characterisation & Optimisation of Battery Banks in Substations (COBBS)

Reference Number
NIA2_NGET0039
Title
Characterisation & Optimisation of Battery Banks in Substations (COBBS)
Status
Completed
Energy Categories
Other Power and Storage Technologies(Electricity transmission and distribution)
Other Power and Storage Technologies(Energy storage)
Research Types
Applied Research and Development
Science and Technology Fields
ENGINEERING AND TECHNOLOGY (Electrical and Electronic Engineering)
UKERC Cross Cutting Characterisation
Not Cross-cutting
Principal Investigator
Project Contact
National Grid Electricity Transmission
Award Type
Network Innovation Allowance
Funding Source
Ofgem
Start Date
01 July 2023
End Date
31 March 2026
Duration
ENA months
Total Grant Value
£592,069
Industrial Sectors
Power
Region
London
Programme
Network Innovation Allowance
Investigators
Principal Investigator
Project Contact, National Grid Electricity Transmission
Web Site
Objectives
ata collection surveys and investigations will be conducted at various NGET substation sites. Testing within the high voltage laboratories at Cardiff University will make use of existing generators and recording instrumentation and laboratory general facilities. The current and voltage measurements will require suitable transducer purchases for the specialist condition monitoring. In addition, computerised data acquisition equipment will be purchased. A possible solution to achieve sizing optimisation would be by utilizing tailored duty cycles based on the independently measured load demands of equipment at NGET"s substations. Expertise from the university will involve work on electrical testing & measurements, laboratory characterisation and battery technologies. Literature survey: Carry out a wider literature survey of DC battery usage in LV systems within transmission substations. Reviewing published literature and examining practice of battery usage on electrical networks in the UK and beyond will reveal any important aspects of battery bank practice that are worth noting going forward. Survey of battery usage on NGET network: Carry out survey of LV equipment connected to substation 110V & 48V DC systems which mainly feeds control and protection equipment through the use of substation batteries on the grid. Work with National Grid engineers to survey and develop an inventory of types of batteries and their typical use on NGET grid network. The survey will also include existing practice for charge/discharge and control of the battery banks. Any available measurement data will be collected and analysed. Development of sensors & transducers: Develop or purchase and install suitable measurement sensors and transducers to monitor DC loads and battery charge/discharge profiles on both centralised and distributed dc systems. Emphasis will be on measurement of current and voltage under both steady state and transient operating conditions. This is a core design, test and calibrate task within the project for both short- and long-term measurements and determination of battery utilisation profiles. It is expected that multiple measurements will be developed and deployed to allow measurement at the battery input/output as well as the direct feed from the alternating current (AC) system and the consumption at the DC energised LV equipment.  Deployment of online condition monitoring: Develop an online condition monitoring system and computerised data acquisition and analysis to obtain short to long-term load profiles and parameters of DC equipment for all LV types of DC equipment tied to the system. It is expected to use the measurement equipment developed in sensors & transducers task above. Explore optimisation of battery usage: Using the characterisation findings above from condition monitoring measurements (transient & steady state standing load), explore the suitability of current Institute of Electrical and Electronics Engineers (IEEE) sizing methodology used by suppliers, and assess possibility of battery sizing optimization.  Application of existing standards for DC standby systems: Survey existing practices used by National Grid in relation to DC standby systems as well as any related standards e.g., International Electrotechnical Commission (IEC) & IEEE standards connected to stationary applications.  Feasibility of new battery chemistries: Exploiting the new knowledge gained from the current battery usage profiles, explore use of battery chemistries not yet used by National Grid and assess any potential advantages and disadvantages for substation standby applications. This should consider whole life value parameters (installation and maintenance requirements, decommissioning) as well as performance aspects.  Standard and industry practice revision: With the findings of this work, explore revision of maintenance standards where applicable. The project objectives can be summarised as to: Understand current battery banks world best practise through a wide literature survey including a survey of battery usage on NGET networkMonitor direct current loads and battery discharge profiles on both centralised and distributed systems to measure current and voltage performance under different steady state or transient operating conditionsAcquire short-term and long-term load profiles through online condition monitoring and computerised data acquisitionConsider standard battery sizing methodologies and possibilities for optimisationReview existing standards for DC standby systemsInvestigate and recommend use of new of battery chemistries not yet used by National Grid and assess any potential benefits Review applicable maintenance standards and industry practiseSupport the energy transition and deliver net benefit through innovation in low voltage direct current systems.
Abstract
Substation battery banks (SBB) in electrical substations participate in black start recovery processes and provide essential back-up power supply for protection, control, telecommunications, and lighting. With stringent limitations on space and increasing requirements for safety and reliability, potential battery sizing optimisation opportunities may be possible to enable reliable, secure, space, time and cost-effective substation energy storage. Battery efficiency with optimal use supports the energy system transition by supporting evolving substation loads requiring appropriate scaling design that avoids costs in either oversizing initial banks or reinstalling entirely new banks. This project considers existing and future battery banks improvements to best practice, better chemistries, and online monitoring techniques with expected benefits in reducing carbon footprint and maintenance costs whilst informing correct & adaptive battery sizing.