Projects: Summary of Projects by RegionProjects in Region Scotland involving Scottish and Southern Energy plc : NIA_SHET_0034 |
||
Reference Number | NIA_SHET_0034 | |
Title | Low Profile 132kV Steel Poles | |
Status | Completed | |
Energy Categories | Other Power and Storage Technologies(Electricity transmission and distribution) 100%; | |
Research Types | Applied Research and Development 100% | |
Science and Technology Fields | ENGINEERING AND TECHNOLOGY (Electrical and Electronic Engineering) 100% | |
UKERC Cross Cutting Characterisation | Not Cross-cutting 100% | |
Principal Investigator |
Project Contact No email address given SSEN Scottish Hydro Electric Transmission |
|
Award Type | Network Innovation Allowance | |
Funding Source | Ofgem | |
Start Date | 01 January 2022 | |
End Date | 31 July 2023 | |
Duration | ENA months | |
Total Grant Value | £1,650,000 | |
Industrial Sectors | Power | |
Region | Scotland | |
Programme | Network Innovation Allowance | |
Investigators | Principal Investigator | Project Contact , SSEN Scottish Hydro Electric Transmission (100.000%) |
Industrial Collaborator | Project Contact , Scottish and Southern Energy plc (0.000%) |
|
Web Site | https://smarter.energynetworks.org/projects/NIA_SHET_0034 |
|
Objectives | Steel alternatives to the wood poles used for trident wood pole construction are required to provide an equivalent solution for the construction of non-resilient overhead lines (OHLs) at altitudes above 300m, where wood poles are impractical, and to provide an alternative supply chain to address the long lead times and creosote obsolescence risk associated with wood poles.Lessons learned during deployments of a composite pole OHL on its transmission network to connect the Dorenell wind farm, and the NeSTS trial OHL at Quoich, are available to inform this work. The most critical of these are that prototypes are utilised at full scale by SSEN and its contractors before the design is frozen, that no accessories requiring frequent inspection are designed to remain mounted to structures, and that the designs are readily manufacturable by multiple companies in response to fully detailed drawings.OHLs constructed with the new steel supports must meet the internal requirements defined for wood poles, and the functional requirements detailed in NeSTS Low Profile 132kV SC Functional Requirements. The project will be split into three work packages to –1. Develop prototype designs.2. Build prototypes and report on performance and subsequent design refinement.3. Conduct type testing for Technical Authority approval. The project objective is to create a low-profile design which replicates the visual consenting envelope, reliability levels, insulation level, and construction methods associated with wood poles, significantly reducing future construction costs. Application of the low-profile design within the existing design suite as a substitute for current steel structures could provide a significant reduction in construction costs to the year ending 2026. Lower construction costs will provide customers with lower cost connections and support energy system transition. | |
Abstract | Steel alternatives to the wood poles used for trident wood pole construction are required to provide an equivalent solution for the construction of non-resilient overhead lines (OHLs) at altitudes above 300m, where wood poles are impractical, and to provide an alternative supply chain to address the long lead times and creosote obsolescence risk associated with wood poles. | |
Data | No related datasets |
|
Projects | No related projects |
|
Publications | No related publications |
|
Added to Database | 26/10/22 |