Techno-Economic Evaluation of Cleaner Coal Fired Plant Operability

Reference Number
DTI/CC/141
Title
Techno-Economic Evaluation of Cleaner Coal Fired Plant Operability
Status
Completed
Energy Categories
Other Power and Storage Technologies(Electric power conversion)
Fossil Fuels: Oil Gas and Coal(Coal, Coal combustion)
Research Types
Applied Research and Development
Science and Technology Fields
SOCIAL SCIENCES (Economics and Econometrics)
ENGINEERING AND TECHNOLOGY
UKERC Cross Cutting Characterisation
Not Cross-cutting
Principal Investigator
Mr S Simpson
E.ON UK (formerly PowerGen)
Award Type
3
Funding Source
DTI
Start Date
01 January 2000
End Date
01 March 2003
Duration
38 months
Total Grant Value
£32,306
Industrial Sectors
Region
East Midlands
Programme
Investigators
Principal Investigator
Mr S Simpson, E.ON UK (formerly PowerGen)
Other Investigator
Project Contact, University of Manchester
Web Site
Objectives

A three year research programme is being undertaken to develop ways of calculating the benefit of plant flexibility as a function of operating regime. This information will be used to evaluate methods for improving plant designs to ensure the optimum trade off between flexibility and other crucial plant parameters such as capital cost, efficiency and reliability. The main aims of the programme are:

  • to develop methods for assessing the costs associated with the operational inflex >ibility of cleaner coal power stations
  • to develop methods of determining the most costeffective trade-off between plant flexibility and other plant characteristics such as efficiency
  • to develop ways of improving the design of cleaner coal power stations
>
Abstract

A three year research programme is being undertaken to develop ways of calculating the benefit of plant flexibility as a function of operating regime. This information will be used to evaluate methods for improving plant designs to ensure the optimum trade off between flexibility and other crucial plant parameters such as capital cost, efficiency and reliability. The main aims of the programme are:

  • to develop methods for assessing the costs associated with the operational inflex >ibility of cleaner coal power stations
  • to develop methods of determining the most costeffective trade-off between plant flexibility and other plant characteristics such as efficiency
  • to develop ways of improving the design of cleaner coal power stations

Electricity markets throughout the world are being reformed and deregulated. One result of this is that power stations are required to operate more flexibly, with more starts and stops and morerapid variat >ions in output. As a result there is considerable commercial pressure being put on manufacturers to provide plant that can be operated flexibly, and on generating companies to buy such plant. However, improving the operational flexibility of a plant almost invariably involves some additional expense, either in terms of increased capital costs or a reduction in efficiency or reliability.

This issue is particularly acute for the new generation of cleaner coal-fired power stations th at a >re now coming on to the market and, in particular, for integrated gasification combined cycle (IGCC) plants, which offer efficient generation of power from coal with excellent environmental performance. However, the operational flexibility of IGCC is believed to be poor and this is one factor inhibiting its uptake. There is thus the need to be able to quantify the costs/benefits associated with plant inflexibility/flexibility in order to design and build new, cleaner coal plants with opti mum >lifetime economic performance.

Powergen UK plc and the University of Manchester Institute of Science and Technology (UMIST) are working together to explore ways in which the costs of plant inflexibility can be quantified. Powergen is contributing its expertise and experience of operating in a variety of liberalised power markets world-wide, whilst UMIST is one of the world s leading centres for the economic optimisation of complex industrial processes.

Data

No related datasets

Projects

No related projects