Abstract:
<p>The objective of the 40mm Serviflex project is to prove the suitability of using a 40mm Serviflex pipe to renew 2" steel on Great Britain's (GB) gas network. The main application that this will be beneficial to is the replacement of the below ground approach mains for network risers. </p> <p>SGN have almost 200 thousand network risers within multiple occupancy buildings throughout its Scotland and Southern networks. A common factor that results in risers being deemed unsuitable and subject to a full replacement is the deterioration of the below ground approach mains sections of risers, which are commonly found to be constructed from 2" steel. Serviflex is a corrugated dual wall liner manufactured by Radius Systems Ltd that when used with specialist installation equipment can negotiate tight bends without compromising its design life. SGN currently utilises the 20mm Serviflex pipe to renew gas mains services up to 1 ¼" back to the original meter position.</p> <p>The use of 40mm Serviflex in riser repair applications will allow the partial repair and refurbishment of existing risers as opposed to the full replacement of them, resulting in reduced time required by SGN and minimising disruptions. It will also allow for these activities to be carried out with less disruption (excavations, lifting floor boards etc.) both within and out with consumers premises. </p> <p>Project recommendations: <bl> <li>Radius Systems draft Gas Industry Standard is to be reviewed by SGN Engineering Policy prior to submission of the draft to the Technical Standards Forum.</li> <li>A further stage is required to test 40mm Serviflex in regards to pressure loss/design flow rate during pipe installations to confirm diameter suitability.</li> <li>A review on proceeding with operational implementation of the product in the network is to be carried out. </li> </bl></p> This report covers the project's: <bl> <li>Introduction</li> <li>Investment options</li> <li>Project delivery</li> <li>Project team structure</li> <li>Field trials</li> <li>Results of field trials</li> <li>Conclusions</li> <li>Recommendations</li> <li>Radius Systems project scope</li> <li>Summary of scheduled deliverables</li> <li>Field trial report</li> <li>Discussion topics</li> <li>Conclusions</li> <li>Recommendations</li> </bl> <ul> <li>Appendix A - Training presentation</li> <li>Appendix B - Trainers manual</li> <li>Appendix C - Training course test paper</li> <li>Appendix D - Course registers</li> <li>Appendix E - Draft GIS/PL5-1:2015</li> <li>Appendix F - SGN draft work instruction</li> <li>Appendix G - Field trial report</li> <li>Appendix H - Cost analysis from 'The Sunshine' pub Farlington</li> <li>Appendix I - Pipe sizing analysis</li> </ul>Publication Year:
2016
Publisher:
Ofgem
DOI:
No DOI minted
Author(s):
SGN
Energy Category
Class Name:
Subclass Name:
Category Name:
Language:
English
File Type:
application/pdf
File Size:
2167750 B
Rights:
Rights not recorded
Rights Overview:
Rights are not recorded within the edc, check the data source for details
Further information:
N/A
Region:
United Kingdom
Related Dataset(s):
No related datasets
Related Project(s):
Related Publications(s):
No related publications