go to top scroll for more

Reducing Energy Losses from Transmission Substations

Reference Number
NIA_SPT_1608
Title
Reducing Energy Losses from Transmission Substations
Status
Completed
Energy Categories
Other Power and Storage Technologies(Electricity transmission and distribution)
Research Types
Applied Research and Development
Science and Technology Fields
ENGINEERING AND TECHNOLOGY (Electrical and Electronic Engineering)
UKERC Cross Cutting Characterisation
Not Cross-cutting
Principal Investigator
Project Contact
SP Energy Networks
Award Type
Network Innovation Allowance
Funding Source
Ofgem
Start Date
01 January 2017
End Date
01 July 2019
Duration
30 months
Total Grant Value
£200,000
Industrial Sectors
Power
Region
Scotland
Programme
Network Innovation Allowance
Investigators
Principal Investigator
Project Contact, SP Energy Networks
Web Site
Objectives
WP1 - Energy Audit Three summary reports to be produced, one for each substation, detailing the energy evaluation and measures implemented. WP2 - Physical monitoring of Substations Energy Breakdown and Analysis An energy breakdown report to be produced to contribute to the main improvement strategy report. WP3 - Building Design Evaluation To produce a report that identifies the potential improvements for the substations and their respective impacts on energy usage and cost. WP4 - Wider Substation Improvements A Quantifiable Improvement report to be written for the wider substations owned and managed by SP Transmission. Each use case will have a distinct success criteria. WP1 - Energy Audit The delivery of three reports showing the key measures which have delivered energy savings at each substation. WP2 - Physical monitoring of Substations Energy Breakdown and Analysis Production of a breakdown analysis of the loading at each of the identified substations, with an evaluation of possible energy control strategies. WP3 - Building Design Evaluation Production of a report which identifies points of improvement for the fabric of the substation buildings, with proposals for improving heating and lighting within the substations. WP4 - Wider Substation Improvements Production of a report showing the improvements which could be made across all transmission substations in the SPT Licence Area, quantifying the benefits of rolling out the changes across SPT.
Abstract
At present, substation energy consumption is uncontrolled and unmonitored. Energy is consumed for a number of processes- heating, battery charging or dehumidifying, for example - to ensure network resilience and ensure the security of the electricity network. Typically, the supply for Grid substations comes from the secondary windings on 33kV neutral earthing transformers, and is unmetered. As such, substation demand is not monitored or accounted for while it contributes to the SPEN transmission losses. This project will initially aim to establish, through audits and metering, the baseline level of energy usage of a number of trial substations in the SPT licence area, and then use the collected data to model the performance of the substation buildings. These data models will allow opportunities for energy efficiency to be identified, then enable the development for a plan for substation energy efficiencyNote : Project Documents may be available via the ENA Smarter Networks Portal using the Website link above
Data

No related datasets

Projects

No related projects

Publications

No related publications

Added to Database
11/12/18